raising the drain and re-turfing at the right-hand side of the 18th green,
re-turfing an area with heather at the 8th hole,
and revetting bunkers at the 11th green
and 3rd fairway.

raising the drain and re-turfing at the right-hand side of the 18th green,
re-turfing an area with heather at the 8th hole,
and revetting bunkers at the 11th green
and 3rd fairway.
Another hard frost expected tonight again.
Can't believe we had a full day of sunshine. Today a few more bunkers were finished.
One at the 9th green,
and one at the 7th green,bunkers also underway at the 3rd fairway.
Other jobs today include turfing at the 10th fairway and spreading iron on the remaining tees from yesterday.
Frost still in the ground this morning, bunker building still carried on at the 2 nd fairway. In the afternoon we managed to dig out a few more bunkers. Even though the turf at the nursery was slightly frozen, we managed to put a few loads of revetting on trailers and workmans. At the end of the day, instead of putting the trailers in the tractor shed we put them in the main building. Hopefully the turf will thaw out with the heat of the building.